How to earn

Yamal LNG Novatek. Yamal LNG company vacancies: shift work

Yamal LNG Novatek.  Yamal LNG company vacancies: shift work

In 2018-2019, Yamal LNG OJSC plans to put into operation one production line plant for the production of liquefied gas, so the question, Yamal LNG - vacancies, is currently very relevant. At Yamal LNG, there are vacancies for specialists and workers of various specialties and qualifications.

Fill out your CV ➤

Vacancies of the YAMAL LNG company in Moscow (office), on duty at Sabetta - an integrated project for the production, liquefaction and supply of natural gas. The project provides for the construction of a plant for the production of liquefied natural gas (LNG) on the resource base of the Yuzhno-Tambeyskoye field. The proven and probable gas reserves of the field according to PRMS standards are 926 billion cubic meters. m. As part of the Project implementation, a transport infrastructure is being created, including sea ​​port and Sabetta international airport.

Company card
YAMAL LNG company: official website - yamallng.ru.
Recent YAMAL LNG vacancies and contacts of the HR department are available at the address, send your resume - yamallng.ru/career/open_vacancies.
Vacancies are posted only on official websites. Through them, access to all contacts and vacancies is open. Without intermediaries from direct employer. Below is information from open sources for familiarization.

Fill out your CV ➤

The company pursues a personnel and social policy in compliance with the most stringent and highest world standards. Yamal LNG vacancies- positions for representatives of various specialties, workers from different countries take part in the implementation of the project.

The construction of the natural gas liquefaction plant is carried out in three stages with the launch in 2017, 2018 and 2019, respectively. The project provides for the annual production of about 16.5 million tons of liquefied natural gas (LNG) and up to 1.2 million tons of gas condensate with supplies to the markets of the Asia-Pacific region and Europe.

Open vacancies Yamal LNG

In addition to the construction of the plant, a modern airport is being built for international communication and seaport, as well as other transport infrastructure facilities. The construction of the plant is carried out in several stages, the launch of which is planned in 2017-2019. Up to 16 million tons of LNG will be supplied annually to Europe and the Asia-Pacific region, in addition, up to 1.2 million tons of gas condensate will be sold.

The project is being implemented by OAO Yamal LNG, whose shareholders are largest companies in the field of production and processing of hydrocarbon raw materials: OAO NOVATEK - 60%, Total - 20%, CNPC - 20%.

Personnel policy

OAO Yamal LNG in its activities complies with high international standards in matters of social and personnel policy. Our project is implemented by representatives of various nationalities and states. A common goal and a strong team are the main conditions for the successful implementation of the Project. The company creates comfortable and safe working conditions, takes care of social security workers, providing compensation, voluntary medical insurance, the possibility of health resorts and recreation.

OAO YAMAL LNG is actively growing company interested in cooperation with highly qualified specialists.

Working conditions in Yamal LNG are constantly improving, so they are safe and comfortable, all workers are provided with a full social package, medical insurance, and there is an opportunity to take advantage of health resorts. The company is actively developing, therefore qualified workers of various specialties are constantly required.

Today, there is a large selection of vacancies, and you can apply for one that matches your education and work experience. The most relevant vacancies: managers, IT-specialists, financial and economic specialists, laboratory assistants chemical analysis, engineers of different areas of work, operators of technological installations.

Accommodations

The stronghold of Yamal LNG is the village of Sabetta, where comfortable conditions for living, recreation and leisure of workers. There are cozy canteens, a hotel, a bathhouse, a sports complex, food warehouses and other facilities. The infrastructure is constantly expanding, a laundry, living quarters, a warm parking lot, a new canteen are being built, so actual vacancies are appearing. More than 15,000 people are already involved in the implementation of this project, and if you hurry, you can soon join them.

Yamal LNG vacancies— an integrated project for the production, liquefaction and sale of gas
Competitive advantages
traditional high concentration reserves located on land
well-studied geology and proven development technologies
very low development and production costs
high efficiency of the liquefaction process due to low average annual temperature
access to the markets of Europe and the Asia-Pacific region
governmental support, including tax incentives

Project infrastructure

The field development project provides for the drilling of 208 wells at 19 well pads. The gas produced at the field will be supplied to international market in the form of LNG, for which a gas liquefaction plant will be built, consisting of three technological lines with a capacity of 5.5 million tons of LNG per year each. The infrastructure for loading LNG for export will consist of an unloading rack with two berths in the port of Sabetta, equipped with ice protection facilities. Reinforced ice-class tankers "Arc7" will be used for LNG transportation.

Yamal LNG - professions for specialists different specialties. The main advantages that allow the company to successfully compete in today's market:

Fill out your CV ➤

  • deposits are located on land and have a high concentration;
  • development technologies are well developed;
  • studied geology;
  • minimum funds are spent on field development and gas production;
  • climatic conditions make it possible to effectively carry out the liquefaction process;
  • established market in Europe and the Asia-Pacific region;
  • tax breaks and other government support.

Many vacancies require people with similar work experience, but there are also those where they accept without work experience, for example, laborers, drivers of various driving categories, there are also vacancies for women.

Project implementation status

The final investment decision on the project was made in December 2013, and the start of LNG production is scheduled for 2017.
The main tenders have been completed and key contracts for the supply of materials and equipment and the provision of design and construction services have been concluded. More than 95% of the LNG plant's output has been contracted. The operation of cargo berths in the port of Sabetta has begun, providing year-round delivery of construction cargo. Production drilling and construction and installation works are underway at the facilities of the LNG plant. At the end of 2016, the project was approximately 75% complete.

It is planned to produce gas from 208 wells, it will be supplied to the market in liquefied form, therefore, starting from 2017, three technological lines are commissioned, each with a capacity of 5.5 million tons of liquefied gas per year.

An unloading rack with two berths is being equipped in the port of Sabetta. Cargo berths are already working, so the delivery of building materials is carried out continuously throughout the year. This project provides for the construction of the largest LNG plant in Russia.

This largest enterprise on the Yamal Peninsula, which provides people in this region with highly paid jobs, average salary is 120,000 rubles. Yamal LNG - vacancies for shift work. Usually shifts are 30/15, 30/30, 60/30, but there may be others, so when applying for a job, be prepared to leave your family, your usual life for a while and work in harsh climatic conditions.

Since the construction of the plant is planned until 2019, the need for new specialists will be relevant for a long time to come.

As part of the Yamal LNG project, it is planned to build the country's largest plant for processing and producing LNG (liquefied natural gas), capable of developing a capacity of about 16,500,000 tons annually based on the resources of the Yuzhno-Tambeyskoye field.
According to PRMS standards, the proven and probable reserves of the gas field are about 900 billion cubic meters. This project involves the implementation of communication paths:
sea ​​port,
transport structure,
modern airport Sabetta.

Work at Yamal LNG

OAO Yamal LNG is one of the leading companies in the region on the Yamal Peninsula, located beyond the Arctic Circle. This venture is a joint venture, where NOVATEK owns a controlling stake, TOTAL, CNPC and the Silk Road Fund are involved.
Salary in Yamal LNG starts from 120,000 rubles.

This structure assumes a large number of jobs for shift work in the North. This direction is widely demanded among applicants who are ready to break away from their usual life and move into conditions of hard work for a period of one month or more. The shift schedule is built mainly as follows: 30/15, 30/30, 60/30 - however, there are other options.
Working conditions
The construction of the plant is planned in three phases:
2017
2018
2019
Accordingly, actual vacancies in the project will appear for a long time. Direct employers are ready to offer Better conditions for shift work in the gas industry.
The Yamal LNG plant is located above the Arctic Circle on the northern Yamal Peninsula, at the site of the South Tambeyskoye natural gas field. Construction is successfully carried out in 3 phases in 2017, 2018 and 2019. The natural gas processing project plans to annually produce liquefied gas from 16.5 million tons and up to 1.2 million tons of gas condensate for the market of the Asia-Pacific region and Europe. Job vacancies at the Yamal LNG plant will be available below.

LNG PLANT IN YAMAL

An LNG plant with a capacity of about 16.5 million tons is being built right at the South Tambeyskoye gas field, in the Gulf of Ob. The construction involves a modular type of installation, which seriously reduces financial expenses for construction and determines the schedule for the implementation of the project. This project will contain 3 natural gas liquefaction lines with a capacity of 5.5 million tons each year. The first launch is planned for 2017. Taking into account the low average Arctic temperatures, much less specific energy is required for the gas liquefaction process, which makes it possible to achieve large volumes of LNG production compared to projects located in the South and using similar equipment. the mixture from the wells of the field will pass through gas gathering networks to a single complex for gas treatment and liquefaction. Further, at the entrance of the complex there will be a separation process. The inlet facilities include units that regenerate methanol and stabilize the condensate. The separated natural gas will go to process lines, where liquefaction and purification from acid gases and methanol will take place, as well as drying and removal of mercury, extraction of ethane, propane and other heavy hydrocarbons. Further, already purified natural gas will be supplied for cooling and liquefaction. LNG will go for further storage in closed-type isothermal tanks. It is planned to build 4 tanks with a capacity of 160,000 cubic meters each. m. each. Work at the LNG plant IN YAMAL vacancies - read on.

Today I read the material of the respected Brekotin .

As always, there are citizens for whom the construction of a new Russian enterprise- like a knife to the heart.

And Russia does not need construction, and the investments are wrong, and the workers are not the same, and the equipment is not right, and the buyers are bastards, everything, without a doubt. Well, God be their judge. Their fate is this - to criticize, sitting in a warm apartment, without taking their ass off the sagging sofa.

And for normal people, I propose to look: what is Yamal LNG- In fact. So: look, and rejoice for our heroic builders and the possibilities of Russian industry.

The whole truth about Yamal LNG

I was again drawn to the north, far, far beyond the Arctic Circle, to the Yamal Peninsula to Sabetta, where one of the largest projects in the oil and gas sector in recent years is being implemented. last years- Yamal LNG. For understanding, $22 billion has already been invested in it (about $27 billion is planned in total). The plant for the production of liquefied natural gas (LNG) will operate on the resource base of the Yuzhno-Tambeyskoye field, and its capacity will be 16.5 million tons per year. In May last year, I was already in these parts http://zavodfoto.livejournal.com/4827701.html, then the overall readiness for the entire project was somewhere around 51.3%, and the readiness for the first stage was 64.4%. How are things today, I'll show and tell everything, good company PAO NOVATEK, the project shareholder, is very open in this matter and is not afraid of me :).

2. Experienced deja vu for a moment. The speaker this time was Dmitry Monakov, already familiar to me, the first deputy director of the project.

3. And immediately to the numbers. At the moment, the overall readiness for the entire project is 77-78%, and for the first stage of the plant it is already 88%. This is how the first stage should look like by the end of the year.

The Yuzhno-Tambeyskoye field is located in the North-East of the Yamal Peninsula and belongs to the West Siberian oil and gas province. It was opened back in 1974. The field consists of 5 shallow gas reservoirs and 37 deep gas condensate reservoirs. The depth of deposits varies from 900 to 2850 m. The size of the deposit from south to north is about 70 km and from east to west - about 30-35 km. In total, it is planned to drill 208 production wells with a horizontal ending at 19 well pads at the field (the necessary 58 wells have already been drilled for the first stage, and a total of 78 have already been drilled at the moment. At the same time, only 35 wells are needed for the second stage, and about 35 for the third -38 The rest will have to maintain the necessary flow for the full operation of the plant). Proved and probable reserves are about 1.3 trillion cubic meters of gas and 60 million tons of condensate. The field development license belongs to Yamal LNG and is valid until 2045. This resource base should be enough for at least 25-30 years of confident work.

The Yamal LNG plant will consist of three gas liquefaction lines with a capacity of 5.5 million tons per year each, i.e. the total capacity will be 16.5 million tons. In addition, the production complex will include liquefied hydrocarbon gas fractionation units, stable condensate and refrigerant storage parks, as well as other general plant engineering systems and flare installations.

The entire plant will be built from 360 modules, of which there will be 111 technological modules. The first such module was delivered to the construction site on September 21, 2015. This basic equipment is produced in 7 Chinese and 3 Indonesian shipyards. The total weight of the LNG plant is 650 thousand tons, of which 150 thousand tons are racks, and 500 thousand tons are the process modules themselves.

In autumn 2016, all 78 modules required for the first stage, including the central control room, were delivered to Sabetta. Nevertheless, 57 modules (for the second and third stages) still remain to be delivered to the territory of the plant, which will appear here according to the plan before the end of 2017.

8. On this day it was below minus 30, and at the height there is still a very strong wind, but can this stop me, who is in love with our industry? Therefore, almost blindly, since all the glasses are fogged up and frozen, I conquer and conquer all the vile heights of the plant :-)

9. Yes, well, in a year they did business here, what they just didn’t build, well done, keep it up, they definitely surprised me!

11. They didn’t hesitate, they walked inside ...

The start of LNG production on the first line is scheduled for 2017, while the first deliveries of liquefied natural gas, from here, should take place before the end of this year.

16.Tanks for storing liquefied gas, there are four of them (4x160,000 m3). In permafrost conditions, each tank is built on a foundation of 948 piles, each 24 meters deep, with a thermal stabilizer installed next to each. In 2016, all of them were built and passed the necessary hydraulic tests. The main platforms of pumping equipment are installed on the first two tanks.

18. We climbed one of the tanks. Their height is 54 meters. By the way, last year I was inside it, but now the way there is booked.

20. An important component of the project is its own generation. A new gas turbine power plant with a capacity of 376 MW will be built here, the thermal power plant will be 160.0 MW. You see, on the right you can see an orange-blue-white building with pipes, this is it. The first gas turbine with a capacity of 47 MW should be launched this spring. Thus, it will create an energy foundation for launching the first stage of the plant. It's no secret that I'm not indifferent to energy, so I'll write a separate post about it.

Concerning production process, it can be briefly described as follows. From the wells, gas is transported to the plant through a pipeline system. They are above ground. Once on the territory of the LNG plant, the gas is slightly prepared so that the liquefaction process takes place in the best possible way. To do this, condensate is separated from the gas (these are liquid fractions that are simply dissolved in the gas at pressure in the reservoir and are in a state like steam), methanol (used for production, such as lubricants) and other unnecessary impurities. By the way, condensate also remains in business, it goes through the pipeline system to special tanks (there are 3 tanks of 50,000 m3 each for this) and when a special tanker arrives, it is also shipped to consumers. Clean (prepared) ideally dry gas is supplied for liquefaction and then for storage in tanks. In addition, in order to obtain a high-quality end product, the oil released during the cleaning process is removed. carbon dioxide and mercury.

On November 13, 2016, cryogenic heat exchangers were delivered to Sabbeta for the second and third stages of the plant, but for the first line, a similar heat exchanger has already been installed at the right place. The main cryogenic heat exchanger is considered the "heart" of the LNG plant, because it is inside it that the final cooling of natural gas to a liquid state is carried out. The heat exchanger itself is made of aluminum alloy and consists of several tube bundles wound around a central core. The total length of the pipes exceeds 43 km.

35. Now about 27,500 people work at the construction site.

40. Our next stop is the Arctic seaport, which is also part of the general infrastructure of the plant. I also wrote about him last time: http://zavodfoto.livejournal.com/4838728.html

41. By the way, thanks to Yamal LNG, the cargo traffic along the Northern Sea Route has doubled. In total, more than 10 million tons of cargo have already been delivered to the seaport of Sabetta since 2012.

Gazprom explained the claims against NOVATEK for ₽30 billion by a “scientist’s letter” ... that statements about the loss of the budget of ₽30 billion due to the project NOVATEK « Yamal LNG' were not official. These assessments were made in a scientific discussion by a member ... blamed the project NOVATEK « Yamal LNG”that the Russian budget missed ₽30 billion. The company's statement was made available to RBC. Claims against NOVATEK were formulated ... with " Yamal LNG» the volume of Russian pipeline gas in European markets. IN NOVATEK refused to recognize these accusations as true. The company emphasized that NOVATEK And... NOVATEK responded to the reproach about the budget loss of ₽30 billion due to Yamal LNG ... Russia received less than 30 billion rubles. In NOVATEK do not consider that liquefied natural gas from the project " Yamal LNG"competes with Russian pipeline gas in..." Nikolai Kislenko critically commented on the launch of liquefied gas production at the plant " Yamal LNG» NOVATEK. « Yamal LNG"is the absence of an export duty, the absence of a mineral extraction tax (tax on the extraction of mineral ... The head of Russia's largest LNG plant moved to NOVATEK ... (LNG) « Yamal LNG NOVATEK received by RBC. The cat will become the 12th member of the board of the company. Among the shareholders Yamal LNG» - the first LNG-factory NOVATEK(owns ... the post of leader " Yamal LNG". "Candidacy for a new CEO « Yamal LNG» will be approved by the board of directors « Yamal LNG"at the end of December 2018," the message says. NOVATEK received in... Mikhelson announced Western pressure on Norway over Russian gas Chapter NOVATEK explained that Western partners are putting pressure on Norway because of the transshipment of liquefied gas from the plant " Yamal LNG". Therefore, it is required to speed up the construction of the terminal in Murmansk, he pointed out. NOVATEK asked to expedite the construction and commissioning of ... an existing plant " Yamal LNG” in Norway has caused pressure on this country from Western partners. About this chapter NOVATEK Leonid Mikhelson said... NOVATEK found gas for the third LNG plant ... good prerequisites for the successful implementation of the new LNG project," he said. NOVATEK launched the first LNG-plant in Yamal - " Yamal LNG- in December 2017. Its capacity ... with reserves of more than 926 billion cubic meters. m of gas. The first two lines Yamal LNG”(together - 11 million tons per year) have already been launched, the third (still ... gas). In May 2018 co-owner NOVATEK And " Yamal LNG» French Total agreed to buy 10% of Arktik LNG-2" and an option for another 5 ...

Business, 24 Sep 2018, 11:12

NOVATEK delivered the first batch of LNG to Brazil ... . Ltd ("daughter" NOVATEK) delivered the first batch of liquefied natural gas (LNG) to Brazil ( LNG) produced at the factory Yamal LNG". This is stated in the message. NOVATEK, received in ... party LNG To China. As Michelson noted, the total share of the two lines of the plant " Yamal LNG» is about 3.5% of the global market LNG. IN NOVATEK plan to produce 55–60 million tons LNG a year, third... NOVATEK Doubled the Remuneration of the Board Members ... the company has launched the first phase of its key gas liquefaction project - " Yamal LNG”(planned capacity - 17.4 million tons per year) - and already ... ACRA Vasily Tanurkov. At the end of July it became known that NOVATEK will start the second queue Yamal LNG» a few months ahead of schedule, and a third earlier... 8 million tons LNG over the plan. In May NOVATEK attracted the first shareholder - the French Total - to its new project"Arctic LNG-2", the launch of which ... The first shipments of liquefied natural gas from Yamal LNG were delivered to China ... the first shipments of liquefied natural gas ( LNG) With " Yamal LNG" To China. It is reported by TASS with reference to NOVATEK. Each tanker carried... " Yamal LNG was launched in early December 2017. Chapter NOVATEK Leonid Mikhelson on July 19 announced the launch of the second phase of " Yamal LNG in the first decade of August. NOVATEK controls 50.1%" Yamal LNG", by 20 ... The head of NOVATEK announced the launch of the second stage of Yamal LNG ... natural gas " Yamal LNG will be launched in the first decade of August. This was stated by the head NOVATEK Leonid Mikhelson, TASS reports. First turn" Yamal LNG» launched in... . The party was acquired by Petronas LNG UK Limited. Gas was delivered by icebreaker LNG- tanker "Christophe de Margerie" to Britain. From there, the cargo was delivered to ... . After running " Yamal LNG" profit NOVATEK increased by 16%, to 179.4 billion rubles. The Russian gas company owns 50.1% Yamal LNG", by 20 ... Timchenko announced a new joint project between Total and NOVATEK ... companies to jointly implement a gas liquefaction project " Yamal LNG” worth $ 27 billion. “We have built now“ Yamal LNG". Where did we get the money? $27 billion investment... . That's what's important. I always have it," Timchenko added. " Yamal LNG» - a plant for the production of liquefied natural gas with a capacity of 16.5 million ... a year (with the possibility of increasing up to 17.5 million tons). Apart from NOVATEK, shareholders " Yamal LNG» are French Total (20%) and Chinese CNPC (20%) and... NOVATEK reported damage to one of the Yamal LNG tankers ... tankers plant " Yamal LNG” has been damaged and will temporarily suspend the supply of liquefied natural gas, Prime reports, citing the deputy board NOVATEK Brand Jetway ... factory " Yamal LNG”at the end of 2017 and an increase in the average selling prices of liquid hydrocarbons and natural gas,” the company said. Factory " Yamal LNG» opened... NOVATEK's revenue increased by 16% after the launch of Yamal LNG ... EBITDA is mainly related to the start of production LNG at the first stage of the plant Yamal LNG» at the end of 2017 and the growth of average prices... . At the annual meeting of shareholders on April 20, the chairman of the board and co-owner NOVATEK Leonid Mikhelson said that according to the results of the first quarter of 2018..., first of all, technological ones,” Mikhelson explained. Factory " Yamal LNG» began production of liquefied natural gas ( LNG) on the first production line in December 2017... The first tanker with gas from Russia for the United States continued its way to Boston ... British terminal Isle of Grain in Kent. Representative of the company NOVATEK, at whose plant liquefied gas was produced, told RBC that ... the purpose of the tanker with the cargo has not changed. NOVATEK On December 5, he announced the launch of the first stage of the plant " Yamal LNG which produces liquefied natural gas. The total capacity of the plant should exceed 16.5 million tons LNG in year. Price... The shipowner named the reason for the turnaround of the tanker with Russian gas for the United States ... delivered to the destination. The change of route there is explained by weather conditions. LNG-Gaselys tanker French company Engie, which carries a cargo of liquefied gas ... were called. They could not name the reasons for the reversal in the company NOVATEK, at the factory " Yamal LNG which this batch of gas was produced. “We sold this one ... we need to ask the new owner - the Engie company,” a representative told RBC on the eve of NOVATEK. At the same time, experts interviewed by RBC did not rule out that ... The first tanker with gas from Russia for the United States turned around in the middle of the Atlantic ... He. NOVATEK December 5, announced the launch of the first stage of the plant " Yamal LNG» for the production of liquefied natural gas with a capacity of 5.5 million tons LNG in year. ​ Until April 2018, gas from " Yamal LNG» will be sold on the spot market, after which deliveries under long-term contracts will begin. " Yamal LNG» 50.1% owned NOVATEK, by 20 ... NOVATEK commented on gas supplies from Yamal LNG to the USA Representative NOVATEK commented on RBC information about the shipment of gas from " Yamal LNG" in USA. "First batch LNG from the factory " Yamal LNG» we sold Petronas and assumed that... the UK's first batch of liquefied natural gas ( LNG) With " Yamal LNG". Kommersant also noted that the cargo LNG originally acquired the British branch of the Malaysian Petronas - Petronas ... . Initially, the first batches of gas were to be delivered to China. NOVATEK owns 50.1%" Yamal LNG”, another 20% each belong to the French Total and the Chinese ... NOVATEK announced plans to become a global player in the LNG market ... Russia by this time, according to the forecast NOVATEK, will produce more than 80 million tons LNG(besides " Yamal LNG» now liquefied gas is produced only at one... new LNG-factories NOVATEK estimates at 2.5–2.8 trillion rubles. (excluding " Yamal LNG”) until 2030, and the operational cash flow LNG-projects by this time, according to the company's forecast, will reach 4-4.3 trillion rubles. NOVATEK ... NOVATEK intends to invest RUB 700–780 billion in gas assets. until 2030 ... first of all " Yamal LNG located in Yamal. According to the strategy NOVATEK, Russia by 2030 will produce about 80 million tons LNG, A NOVATEK will provide two... market LNG amounted to almost 30%. Before the launch Yamal LNG» Russia exported about 10 million tons LNG per year from the Sakhalin-2 plant of Gazprom. NOVATEK stated that it would be possible to reach the level of Qatar after the launch of two LNG-projects of the company: Yamal LNG” and “Arctic LNG-2". ​ Technological solution: why Russia needs LNG production in the Arctic ... NOVATEK, which is the key shareholder Yamal LNG". The success is obvious. But more importantly, what's next? First, it is interesting and important what proportion of tankers with LNG... liquefaction LNG, but also Gazprom, and NOVATEK making efforts to create own technologies and localize the production of equipment. It is assumed that the fourth line Yamal LNG" will... NOVATEK named the buyer of the first batch of gas from Yamal LNG ... . This is stated in a message received by RBC. NOVATEK, which owns 50.1%" Yamal LNG». NOVATEK on Tuesday, December 5, announced the launch of the first ... in a message NOVATEK. Chairman of the Board and co-owner NOVATEK Leonid Mikhelson told reporters on December 8 that the first shipments of liquefied gas from the project " Yamal LNG» will be directed... to the largest exporters LNG in the world,” Mikhelson said (his words are quoted in the company’s message). Apart from NOVATEK at " Yamal LNG» three more shareholders: by... Gas concession: how the state helped build Yamal LNG ... governments with export liberalization LNG. Initially, it was assumed that exporting liquefied gas from “ Yamal LNG” will be Gazprom Export, with which NOVATEK in 2010 concluded ... a supply contract, under which the shareholders " Yamal LNG»could mortgage loans. Shortly after the long-awaited export liberalization LNG(November 2013) were introduced... Saudi minister attends opening of NOVATEK's Yamal LNG plant ... the village of Sabetta for the opening ceremony of the plant " Yamal LNG", controlled NOVATEK, and loading the first batch of liquefied natural gas ( LNG) arrived the Minister of Energy, Industry and Natural ... June, at the same time he met with the co-owner NOVATEK Leonid Michelson. Shareholders " Yamal LNG» besides NOVATEK(50.1%) are the French concern Total and the Chinese... ... from the project " Yamal LNG NOVATEK(controls 51% " Yamal LNGYamal LNG NOVATEK, shareholders " Yamal LNG The first tanker with Yamal LNG products will be sent to Chinese CNPC ... from the project " Yamal LNG”, which is scheduled to be launched before the end of 2017, will be shipped to China's CNPC, said CFO NOVATEK(controls 51% " Yamal LNG”) Mark Jetway ... the turn of the plant “ Yamal LNG"is ready for 97%, the entire project as a whole - for 89%, according to the materials of the company. Apart from NOVATEK, shareholders " Yamal LNG» are the French Total... The head of the company associated with the Yamal LNG project faces a criminal case ... « Yamal LNG”, we recall, is building a plant for the production of liquefied natural gas in the YaNAO ( LNG). The project provides for an annual production of about 16.5 million tons LNG and... in 2017, 2018 and 2019 respectively. Shareholders of JSC " Yamal LNG» are PJSC « NOVATEK"(50.1%; co-owner and chairman of the board of the company Leonid Mikhelson ... failed to do this. Journalists also turned to" NOVATEK" And " Yamal LNG' has not yet been answered. The workers warned the governor of a hunger strike due to non-payment of wages Employees of "RSK-Logistic" who worked on the construction of the project " Yamal LNG"(the largest shareholder of JSC" Yamal LNG" company " NOVATEK”), told the Governor of St. Petersburg Georgy Poltavchenko that ... in 2017, 2018 and 2019, respectively. Shareholders of JSC " Yamal LNG» are PJSC « NOVATEK"(50.1%; co-owner and chairman of the board of the company Leonid Mikhelson ... NOVATEKYamal LNG NOVATEK Yamal LNG LNG LNG NOVATEK ... The head of the Federal Antimonopoly Service called the conditions of the competition in Yamal "outrageous" ... this region. These conditions apply only NOVATEK building a gas liquefaction plant in Yamal " Yamal LNG, and its child structures. “I don't... 285.3 billion cubic meters. m (D1). NOVATEK is building a plant for the production of liquefied natural gas " Yamal LNG» with a capacity of 16.5 million tons in... other LNG-projects in Yamal and Gydan, for example, "Arktik LNG-2" on the basis of the Salmanovskoye and Geophysical fields. At the end of June, CFO NOVATEK ... Yamal LNG", controlled NOVATEKYamal LNGYamal LNGYamal LNG» are NOVATEK (50 ... Yamal LNG to charter four LNG carriers from a Japanese company ... . (MOL) has signed a long-term contract for the charter of four gas carriers for the project " Yamal LNG", controlled NOVATEK. The capacity of the tanks of each vessel will be 174 thousand cubic meters. m... Greek Dynagas. With these companies Yamal LNG signed 45-year contracts for transportation. The first stage of the plant Yamal LNG» with a capacity of 16.5 million tons should be launched at the end of 2017. The project is estimated at $27 billion. Shareholders Yamal LNG» are NOVATEK (50 ... NOVATEKYamal LNGYamal LNG NOVATEK Yamal LNG will refuse €300 mln of Chinese financing in favor of loans ... said the chairman of the board of the gas company " NOVATEK» Leonid Mikhelson, RBC correspondent reports. Michelson confirmed that the first line " Yamal LNG"will be put into operation in ... Germany, in the amount of about € 300 million. " Yamal LNG» - a project for the production, liquefaction and supply of natural gas. NOVATEK plans to launch the first enterprise of the project to... Company NOVATEK attract to the project Yamal LNG NOVATEK Yamal LNGYamal LNG» - a project for the production, liquefaction and supply of natural gas. NOVATEK Yamal LNG at the end of 2017... NOVATEK will attract €200 million from Germany and Sweden to Yamal LNG Company NOVATEK attract to the project Yamal LNG» more than €200 million from financial institutions Germany and Sweden. This was stated by the head NOVATEK Leonid Mikhelson, reports TASS. According to the agency, about attracting funds from Germany and Sweden to the project " Yamal LNG"Mikhelson told... €200 million," Mikhelson said. " Yamal LNG» - a project for the production, liquefaction and supply of natural gas. NOVATEK expects to launch the first plant " Yamal LNG at the end of 2017... Novatek intends to attract Spaniards to projects in Yamal ... Novatek” did not rule out the possibility of attracting Spanish companies to the new project for the production of liquefied natural gas “Arktik LNG-2". The plant will appear on the shelf... business forum. With a number of foreign and Russian companies project " Novatek has already reached an agreement. In particular, a framework agreement was signed on a strategic ... . Start of construction LNG- the plant is planned for 2018, the launch of the first line (there will be three in total) - in 2022. Talking about " Yamal ...) - non-core business for NOVATEK who focused on the development of large LNG-factories in Yamal and the Gydan Peninsula. First of all " Yamal LNG» with a capacity of 16.5 million times, estimates the head of the LNG ICIS Heren Roman Kazmin. LNG for Poland NOVATEK has already begun to develop in the market of small-tonnage LNG, and Cryogas-Vysotsk can...

Competitive advantages

    traditional high concentration reserves located on land

  • well-studied geology and proven development technologies
  • very low development and production costs
  • high efficiency of the liquefaction process due to low average annual temperature
  • access to the markets of Europe and the Asia-Pacific region
  • government support, including tax incentives


Project infrastructure

The field development project provides for the drilling of 208 wells at 19 well pads. The gas produced at the field will be supplied to the international market in the form of LNG, for which a gas liquefaction plant will be built, consisting of four technological lines. The first line of the plant with a capacity of 5.5 million tons of LNG per year was put into operation in December 2017. The infrastructure for loading LNG for export consists of an unloading rack with two berths in the port of Sabetta, equipped with ice protection facilities. Reinforced ice-class tankers Arc7 are used for LNG transportation.

Project implementation status

The final investment decision on the project was made in December 2013.

LNG production on the first production line of the plant started on December 5, 2017. Yamal LNG shipped the first batch of 170 thousand cubic meters of liquefied natural gas on December 8, 2017. In August 2018, Yamal LNG shipped the first batch of LNG after the launch of the plant's second process line. In November 2018, Yamal LNG produced the first LNG at the third production line.

And I was again drawn to the north, far, far, beyond the Arctic Circle to the Yamal Peninsula to Sabetta, where one of the largest projects in the oil and gas sector in recent years, Yamal LNG, is being implemented. For understanding, $22 billion has already been invested in it (about $27 billion is planned in total). The plant for the production of liquefied natural gas (LNG) will operate on the resource base of the Yuzhno-Tambeyskoye field, and its capacity will be 16.5 million tons per year. In May last year, I was already in these parts, then the overall readiness for the entire project was somewhere around 51.3%, and the readiness for the first stage was 64.4%. How things are today, I will show and tell everything, since NOVATEK PJSC, the project shareholder, is very open in this matter and is not afraid of me :).


2. I experienced deja vu for a moment. The speaker this time was Dmitry Monakov, already familiar to me, the first deputy director of the project.

3. And immediately to the numbers. At the moment, the overall readiness for the entire project is 77-78%, and for the first stage of the plant it is already 88%. This is how the first stage should look like by the end of the year.

The Yuzhno-Tambeyskoye field is located in the North-East of the Yamal Peninsula and belongs to the West Siberian oil and gas province. It was opened back in 1974. The field consists of 5 shallow gas reservoirs and 37 deep gas condensate reservoirs. The depth of deposits varies from 900 to 2850 m. The size of the deposit from south to north is about 70 km and from east to west - about 30-35 km. In total, it is planned to drill 208 production wells with a horizontal ending at 19 well pads at the field (the necessary 58 wells have already been drilled for the first stage, and a total of 78 have already been drilled at the moment. At the same time, only 35 wells are needed for the second stage, and about 35 for the third -38 The rest will have to maintain the necessary flow for the full operation of the plant). Proved and probable reserves are about 1.3 trillion cubic meters of gas and 60 million tons of condensate. The field development license belongs to Yamal LNG and is valid until 2045. This resource base should be enough for at least 25-30 years of confident work.

The Yamal LNG plant will consist of three gas liquefaction lines with a capacity of 5.5 million tons per year each, i.e. the total capacity will be 16.5 million tons. In addition, the production complex will include liquefied hydrocarbon gas fractionation units, stable condensate and refrigerant storage parks, as well as other general plant engineering systems and flare installations.

The entire plant will be built from 360 modules, of which there will be 111 technological modules. The first such module was delivered to the construction site on September 21, 2015. This basic equipment is produced in 7 Chinese and 3 Indonesian shipyards. The total weight of the LNG plant is 650 thousand tons, of which 150 thousand tons are racks, and 500 thousand tons are the process modules themselves.

In autumn 2016, all 78 modules required for the first stage, including the central control room, were delivered to Sabetta. Nevertheless, 57 modules (for the second and third stages) are still envying the territory of the plant, which will appear here according to the plan before the end of 2017.

8. On this day it was below minus 30, and at the height there is still a very strong wind, but can this stop me, who is in love with our industry? Therefore, almost blindly, since all the glasses are fogged up, I conquer and conquer all the vile heights of the plant :-)

9. Yes, well, in a year they did business here, what they just didn’t build, well done, keep it up, they definitely surprised me!

11. They didn’t hesitate, they walked inside ...

The start of LNG production on the first line is scheduled for 2017, while the first deliveries of liquefied natural gas from here should take place before the end of this year.

16. Liquefied gas storage tanks, there are four of them (4x160,000 m3). In permafrost conditions, each tank is built on a foundation of 948 piles, each 24 meters deep, with a thermal stabilizer installed next to each. In 2016, all of them were built and passed the necessary hydraulic tests. The main platforms of pumping equipment are installed on the first two tanks.

18. We climbed one of the tanks. Their height is 54 meters. By the way, last year I was inside it, and now the way there is booked.

20. An important component of the project is its own generation. A new gas turbine power plant with a capacity of 376 MW will be built here, the thermal power plant will be 160.0 MW. You see, on the right you can see an orange-blue-white building with pipes, this is it. The first gas turbine with a capacity of 47 MW should be launched this spring. Thus, it will create an energy foundation for the launch of the first stage of the plant. It's no secret that I'm not indifferent to energy, so I'll write a separate post about it.

As for the production process, it can be briefly described as follows. From the wells, gas is transported to the plant through a pipeline system. They are above ground. Once on the territory of the LNG plant, the gas is slightly prepared so that the liquefaction process takes place in the best possible way. To do this, condensate is separated from the gas (these are liquid fractions that are simply dissolved in the gas at pressure in the reservoir and are in a state like steam), methanol (used for production, such as lubricants) and other unnecessary impurities. By the way, condensate also remains in business, it goes through the pipeline system to special tanks (there are 3 tanks of 50,000 m3 each for this) and when a special tanker arrives, it is also shipped to consumers. Pure (prepared) ideally dry gas is supplied for liquefaction and then for storage in tanks. In addition, in order to obtain a high-quality end product, carbon dioxide and mercury released during the purification process are removed.

On November 13, 2016, cryogenic heat exchangers for the second and third stages of the plant were delivered to Sabbata, but for the first line, a similar heat exchanger has already been installed at the right place. The main cryogenic heat exchanger is considered the "heart" of the LNG plant, because it is inside it that the final cooling of natural gas to a liquid state is carried out. The heat exchanger itself is made of aluminum alloy and consists of several tube bundles wound around a central core. The total length of the pipes exceeds 43 km.

35. Now about 27,500 people work at the construction site.

41. By the way, thanks to Yamal LNG, the cargo traffic along the Northern Sea Route has doubled. In total, more than 10 million tons of cargo have already been delivered to the seaport of Sabetta since 2012.

44. At the moment, the construction of the preparatory period facilities necessary for the delivery of LNG plant modules has been completed. Six cargo berths have been built and the construction of berths for loading LNG and gas condensate is being actively continued.